Resources, Reserves & Cut-off Grade

Not all mineralised rock is ore. Learn the difference between mineral resources (inferred, indicated, measured) and ore reserves (probable, proved) under JORC / NI 43-101, how the breakeven cut-off grade is calculated from price, recovery and costs, and how grade–tonnage curves show the effect of changing cut-off.

Ore is rock that can be mined, processed and sold at a profit. Whether a block of rock is ore or waste depends on metal price, costs and recovery — so the same deposit can grow or shrink as markets change.

Public reporting codes (JORC in Australia, NI 43-101 in Canada, SAMREC, S-K 1300) protect investors by requiring a Competent/Qualified Person to sign off estimates.

An analogy

Cut-off grade is like the minimum tip that makes a delivery trip worthwhile: below it, the effort costs more than you earn.

Resources vs reserves

A Mineral Resource has reasonable prospects of eventual economic extraction: Inferred (low confidence), Indicated and Measured (highest). An Ore Reserve is the part of Indicated/Measured resources that is economically mineable after applying 'modifying factors' — mining, processing, economic, legal, environmental, social: Probable and Proved.

Cut-off grade

Blocks above cut-off go to the mill; below go to waste or low-grade stockpiles. The marginal cut-off (for rock that must be mined anyway) uses only processing costs; the breakeven cut-off includes mining cost. Higher prices or recoveries lower the cut-off and increase reserves.

Grade–tonnage curves

Plot tonnage above cut-off and average grade above cut-off versus cut-off. Raising cut-off reduces tonnage but raises average grade — a trade-off between mine life and early cash flow.

Lane's theory and dilution

Kenneth Lane's method finds cut-offs that maximise NPV considering mine, mill and market constraints — often higher early in life. Real mining also includes dilution (waste mixed in) and ore loss, which must be applied when converting resources to reserves.

Formulas

Worked example: Copper cut-off grade

Given: Cu price $9.0/kg, selling cost $0.5/kg; Recovery 88 %; Processing $12/t, G&A $3/t, mining $2.5/t

Find: Mill and breakeven cut-offs.

Answer: 0.20 % (mill) and 0.23 % (breakeven)

Worked example: Effect on tonnage

Given: Exponential deposit: T₀ = 200 Mt, μ = 0.5 %

Find: Tonnage and grade above 0.20 % and 0.40 %.

Answer: Doubling cut-off cuts tonnage by one-third but raises grade 29 %

Common mistakes

Applications

Key takeaways

Going further