Haul Trucks & Fleet Sizing
Haul trucks move most material in open pits. Learn truck classes, rolling and grade resistance, rimpull and speed, cycle time components, match factor, fleet size, productivity, fuel/energy and trolley assist, and truck dispatch.
Ultra-class trucks carry 220–400 t, cost over $5 million each and burn ≈ 100–200 L of diesel per hour. Haulage is often the largest single mining cost, so accurate fleet sizing and efficient roads matter enormously.
An analogy
A haul truck climbing a ramp is like cycling uphill with a heavy backpack: the grade and soft ground both resist you, and your legs (engine power) set the top speed.
Resistance
Grade resistance ≈ 1 % per 1 % of slope; rolling resistance ≈ 2 % on good roads, 4–5 % on poor roads, more on soft ground. Every 1 % of rolling resistance on a ramp acts like an extra 1 % of grade.
Rimpull and speed
Manufacturer rimpull–speed curves give maximum speed for a given total resistance; retarding curves limit downhill speed. Travel times per segment are summed to get cycle time; simulation (TALPAC, FPC) automates this.
Fleet sizing
Trucks per loader = cycle time ÷ loading time (including spotting). Match factor ≈ 1 balances fleet; < 1 means the shovel waits; > 1 means trucks queue. Dispatch systems (Modular, Wenco) assign trucks dynamically.
Energy and electrification
Trolley assist powers diesel-electric trucks from overhead lines on ramps (faster, less fuel). Battery-electric and hydrogen trucks are being trialled to decarbonise haulage — the largest source of mine Scope 1 emissions.
Formulas
- Resisting force:
F = GVW × g × TR - Power at speed:
P = F × v - Truck cycle:
t_c = load + spot + haul + dump + return - Trucks per loader:
N = t_c / (load + spot) - Match factor:
MF = N_trucks × load time / (N_loaders × truck cycle)
Worked example: Force and power on a ramp
Given: GVW 380 t (160 empty + 220 payload); Grade 10 % + RR 2 %, speed 12 km/h
Find: Resisting force and power.
- F = 380 × 9.81 × 0.12 = 447 kN
- P = 447 × 3.33 = 1490 kW
Answer: 447 kN, ≈ 1.5 MW
Worked example: Fleet for one shovel
Given: Load 1.5 + spot 0.5 + haul 10 + dump 1.5 + return 6 min; Payload 220 t
Find: Trucks and production.
- Cycle = 19.5 min; loading slot = 2 min → N = 9.75 → 10 trucks
- Per truck = 220 × 60/19.5 = 677 t/h
- Fleet ≈ 6770 t/h (shovel-limited)
Answer: 10 trucks, MF ≈ 1.03
Common mistakes
- Wrong: Ignoring rolling resistance. — Right: Poor roads add grade-equivalent resistance.
- Wrong: Sizing fleet to average cycle only. — Right: Cycles grow as pits deepen — plan year by year.
Applications
- Fleet planning: Truck numbers for each year of the mine plan.
- Dispatch: Real-time assignment to reduce queuing.
- Decarbonisation: Trolley assist and battery trucks.
Key takeaways
- F = GVW g (GR + RR).
- Cycle = load + haul + dump + return.
- N = cycle/load time; MF ≈ 1.
- Plan fleets as pits deepen.
Going further
- Haulage simulation: TALPAC/FPC with rimpull curves.
- Dispatch optimisation: Linear programming for truck assignment.
- Battery trucks: Charging strategies and regenerative braking.